- Order a quality concrete mix with the appropriate slump for proper placement required.
- Place concrete on a well-drained sub-grade that has adequate and uniform load-bearing characteristics.
- Grade the sub-grade so that the concrete is of uniform thickness and properly sloped for drainage.
- Vibrate or tamp and screed the concrete, then float it to the specified grade, flatness, and levelness.
- Texture all surfaces adequately and uniformly for slip resistance.
- Finish all surfaces within reasonably the same time after placement.
- Finish the edges first and do all hand-finishing in the same direction.
- Protect the concrete surface from rapid evaporation of bleed water.
- Use an approved curing compound for proper curing of concrete.
- Protect the freshly placed concrete from freezing for the first 72 hours.

- Don't use calcium chloride accelerators to achieve fast concrete set time.
- Don't order concrete in less than 3 yd3 (2 m3) increments. Full color consistency is not guaranteed.
- Don't place concrete on a sub-grade that is not thoroughly compacted and dampened.
- Don't place concrete over freestanding water or muddy, frozen or soft spots.
- Don't add water after a portion of the load has been discharged, or retemper concrete that has started to set.
- Don't sprinkle water, or otherwise add water to the surface during finishing operations.
- Don't use inconsistent finishing practices.
- Don't over-trowel (burn or burnish) the concrete surface.
- Don't use plastic sheeting to cure color concrete.
- Don't allow items to stand on concrete during the curing process.
|
|
 |
 |